Anaklia Breaks Ground

Georgia moved the Anaklia deep-sea port into active construction in April 2026, with Belgium's Jan De Nul building a 1.38 km breakwater and an 18 m channel.

SGBA Published About events of 24 Apr 2026 4 min read

Anaklia port, first stage of works (schematic)BLACK SEAGEORGIABreakwater: about 1.38 kmAccess channel dredged to about 18 mAnakliaDeep-sea port sitePotiExisting portBatumi (further south)Contractor: Jan De Nul (Belgium)First vessel expected: 2029Rail link: 18 km line planned
24 Apr 2026active construction begins
~1.38 kmbreakwater
~18 mchannel depth
~$1.1bntotal project cost
Schematic, not to scale. Sources: Xinhua via The Star, Jamestown Foundation, Imedi. Graphic: SGBA.

What happened

On 24 April 2026 Georgia announced that the Anaklia deep-sea port on the Black Sea had moved into active construction. Tamar Ioseliani, Deputy Minister of Economy and Sustainable Development, said the step followed the completion of preparatory works at the site.

The contractor is Belgium’s Jan De Nul, one of the world’s largest dredging and marine construction companies. The first stage covers two things: a breakwater of about 1.38 km, and dredging of the access channel to a depth of roughly 18 metres. Ioseliani linked the port to Georgia’s wider transport programme, including upgrades to railways and highways and a planned new international airport at Vaziani, near Tbilisi.

What a breakwater and a channel do

A port on an open coast needs two pieces of marine engineering before any quay or crane can be built. The breakwater is a long wall of rock and concrete armour units built out into the sea. It shelters the harbour from waves and swell, so ships can berth and cargo can be handled in most weather. On the Black Sea, where winter storms can be severe, it decides how many days a year the port can work.

The access channel is the dredged route that ships use to approach the berths. Its depth sets the size of ship the port can take. At about 18 metres, Anaklia’s channel is designed for large vessels that cannot enter Georgia’s existing ports. Dredged material is often reused to reclaim land for terminals and storage yards behind the quay.

Why depth matters for Georgia

Georgia’s two main seaports, Poti and Batumi, are relatively shallow and hemmed in by their cities. They handle most of the country’s trade, and a growing share of Middle Corridor cargo, but they cannot take the large Panamax-class ships that carry much of today’s container and bulk trade. Anaklia, on the coast north of Poti near the mouth of the Enguri river, is Georgia’s only planned port deep enough for them.

For the Middle Corridor, larger ships on the Black Sea leg mean a lower cost per container between the Caucasus and Europe. That matters because the corridor’s main commercial weakness is cost: every change between train, ship and truck adds handling charges. A deep-water port lets cargo that has crossed Central Asia, the Caspian and the South Caucasus move on to Romania, Bulgaria or the Mediterranean in larger, cheaper loads.

A project with a long history

Anaklia has been announced, tendered and cancelled more than once since 2016. A consortium of Georgia’s TBC Holding and the US-based Conti Group won the first contract that year; the government terminated it in 2020. A Chinese-led consortium headed by CCCC was selected in 2024 for a 49% stake. The April start of marine works was the first physical evidence in years that the port was actually being built.

Ownership was still open at this point. Three months later, in July, the government announced that the state would own the port and lease individual terminals to operators, after the Chinese-led group withdrew without signing. Economy Minister Mariam Kvrivishvili put the total cost at about $1.1bn and said the first vessel is expected in 2029. See our analysis: Georgia takes Anaklia back.

The land side

A port is only as useful as its links inland. In May Prime Minister Irakli Kobakhidze announced that “a new 18-kilometer railway line connecting Anaklia Port will be built”, as part of a ten-year, $1.7bn modernisation of Georgian Railway. Georgian Railway’s director general, Lasha Abashidze, said the line would take two to two and a half years to build, and that a freight station would serve the port. A World Bank-backed tender for supervision of the rail link was published in October, covered in a separate article.

What it means for business

  • Marine contractors and suppliers: the first stage is under way, but quays, terminals, rail and road links and utilities will follow, each with its own contracts.
  • Terminal operators: under the state-owned model chosen in July, container, bulk and logistics terminals will be tendered separately.
  • Shippers: until 2029, Black Sea cargo on the corridor continues to move through Poti, Batumi and Türkiye’s ports. Anaklia is a medium-term option, not a near-term one.

What to watch

  • Progress on the breakwater and the channel through 2027.
  • The rail and road links to the port, which decide how much cargo it can actually handle.
  • Terminal tenders under the state-owned model, and who bids.

SGBA view

April 2026 is when Anaklia moved from plan to construction site. Marine works by a top-tier European contractor give the project a credibility it has lacked for a decade. The harder questions, about financing, operators and cargo, were still to come, and the government answered the first of them in July.

By SGBA. Figures as reported at the time of writing.

Sources

  1. Xinhua via The Star, "Georgia embarks on active construction of Anaklia port", 25 April 2026
  2. Jamestown Foundation, Eurasia Daily Monitor, "Georgia's Anaklia pivots to state ownership", 16 July 2026
  3. Imedi, "Georgia to invest $1.7 billion in railway overhaul over next decade, says Georgian PM", May 2026

SGBA checks every figure against the original source. How we work