The Black Sea Power Cable Moves to Engineering

The 1,155 km, 1,300 MW power cable from Georgia to Romania entered technical preparation in 2026, with a seabed survey next and operation targeted for 2032.

SGBA Published About events of 29 Jul 2026 3 min read

Black Sea power cable (schematic)ROMANIABLACK SEATÜRKIYEGEORGIAUKRAINEAbout 1,115 km under the seaConstanța areaTopraisar substationAnakliaDepths over 2,500 m
~1,155 kmtotal length
1,300 MWplanned capacity
±525 kVdirect current (HVDC)
2032target for operation
  1. 2024CESI feasibility study.
  2. Early 2026Transelectrica and GSE sign a memorandum (not an investment decision).
  3. Apr 2026EU lists it as a project of mutual interest.
  4. 30 Jul 2026Workshop prepares the marine survey.
  5. 2027–28Marine studies, environmental assessment, business model.
  6. 2032Target start of operation.
Schematic, not to scale. Sources: Romania Insider, AGERPRES, Argus. Graphic: SGBA.

What happened

The planned high-voltage power cable under the Black Sea between Georgia and Romania moved from study to technical preparation in 2026. Early in the year Romania’s grid operator Transelectrica and Georgian State Electrosystem (GSE), Georgia’s grid operator, signed a memorandum of understanding. In April the project was given the status of a Project of Mutual Interest (PMI) by the EU, which makes it eligible for EU funding and faster permitting.

On 30 July Transelectrica hosted a workshop to prepare the marine survey. GSE, Italy’s engineering consultancy CESI, Romania’s Maritime Hydrographic Directorate and the Romanian Border Police took part. They discussed the seabed survey, the route, permits, the schedule and costs. The World Bank is supporting the preparation phase.

The memorandum is not a final investment decision. That will come only after the surveys, studies and a business model are complete.

The project

  • Route: from Anaklia on Georgia’s coast to the Topraisar substation near Constanța in Romania.
  • Length: about 1,155 km, of which about 1,115 km under the sea and 40 km on land.
  • Capacity: about 1,300 MW, using high-voltage direct current (HVDC) at ±525 kV, according to CESI’s 2024 feasibility study.
  • Depth: parts of the route are deeper than 2,500 m, which makes it one of the more technically demanding cable projects of its kind.
  • Timeline: consultants for the seabed surveys in 2026, marine studies, environmental assessment and the business model in 2027–28, and a target of operation in 2032.
  • Cost: not yet published.

Why direct current

Most power grids run on alternating current (AC). Over very long distances, and especially under the sea, AC cables lose too much energy. High-voltage direct current (HVDC) cables lose much less, so long subsea links almost always use DC, with converter stations at each end to switch between DC and the AC used on land. The two converter stations are among the most expensive parts of such a project.

Why it matters

The cable is the electricity side of the Middle Corridor. Railways and ports move goods west; this cable would move power. It would connect Georgia, and through Georgia potentially Azerbaijan and Central Asia, directly to the EU grid without crossing Russia or Türkiye. Much of that power could come from hydro, wind and solar.

Georgia’s own power market is changing to make this possible. It launched day-ahead and intraday markets in 2024, works with Nord Pool, and plans full liberalisation in 2027. Zviad Gachechiladze, a GSE board member, told Argus that the cable would be used for export about 90% of the time, and that “no regulatory barriers have been identified that cannot be overcome”. GSE is also preparing a 200 MWh battery storage system near Tbilisi, financed by the Asian Development Bank, by 2028.

The cable would land at Anaklia, where Georgia is also building its deep-sea port (Anaklia explained).

What it means for business

  • Renewable developers in Georgia and Azerbaijan: access to EU power prices would make large wind, solar and hydro projects easier to finance.
  • Cable and marine contractors: seabed surveys and engineering studies come first. The main supply and installation contracts would follow a final investment decision.
  • Energy traders: Georgia’s market reforms and the link to Nord Pool create new trading opportunities even before the cable exists.

What to watch

  • The award of seabed survey contracts.
  • Publication of the updated cost estimate.
  • Financing from the EU, the World Bank and other lenders.
  • Any decision to extend the link toward Azerbaijan and the Caspian.

SGBA view

The Black Sea cable is still years from a final decision, and its cost will decide its fate. In 2026 it moved from idea to engineering, which is the step most large projects never reach. For the Middle Corridor it adds something the railways cannot: a reason for Europe to see the South Caucasus as an energy partner, not only a transit route.

By SGBA. Figures as reported; specifications may change with the updated studies.

Sources

  1. Romania Insider, "Transelectrica reports progress on Black Sea power interconnector", July 2026
  2. AGERPRES, "Georgia–Romania submarine cable project advances to marine survey preparation stage", 30 July 2026
  3. Argus, "Q&A: Black Sea power line set for 2032 operation: GSE", January 2026

SGBA checks every figure against the original source. How we work