Finance · PortsAnalysis

Georgia Takes Anaklia Back: What the State-Owned Model Means for Investors

After the Chinese-led consortium left, Georgia will own and build the $1.1bn Anaklia deep-sea port and lease its terminals. First ship planned for 2029.

SGBA Published About events of 6 Jul 2026 5 min read

Who was meant to own Anaklia port
2016: concession to Anaklia Development Consortium (TBC Holding and Conti Group). Cancelled in 2020.
Private consortium
2024: CCCC-led Chinese consortium selected for 49%. Left in 2026 without signing.
Georgian state 51%CCCC-led 49%
July 2026: state-owned landlord model
Georgian state owns the port
How a landlord port works
State buildsBreakwater, dredging, quays, rail and road links
State ownsLand and core infrastructure stay public
Operators leaseContainer, bulk and logistics terminals tendered one by one
Operators equipCranes, yards and systems paid by each tenant
~1.38 kmbreakwater, first stage
~18 maccess channel depth
~$1.1bntotal project cost
2029first vessel expected
Sources: Jamestown Foundation, Xinhua via The Star. Graphic: SGBA.

What happened on 6 July

On 6 July 2026 Georgia’s Minister of Economy and Sustainable Development, Mariam Kvrivishvili, announced that the Anaklia deep-sea port will be developed and owned by the Georgian state. It will be run on a “landlord model”: the state builds and keeps the core infrastructure, and invites other states and international companies to lease and equip individual terminals.

Prime Minister Irakli Kobakhidze said the model “will ensure the safety of our sovereign interest and diversity of partners”. Kvrivishvili added that she remained “optimistic and hoped to see the Chinese side participate as a partner”, according to Business Media Georgia as cited by the Jamestown Foundation.

The decision followed the exit of the Chinese-led group chosen in 2024. That consortium, led by China Communications Construction Company (CCCC), was due to take a 49% stake. It withdrew without ever signing an investment agreement.

Why Anaklia matters

Georgia’s existing Black Sea ports, Poti and Batumi, are relatively shallow and space-constrained. They cannot take the large Panamax-class ships that carry much of today’s container and bulk trade. Anaklia, on the coast north of Poti near the mouth of the Inguri river, is Georgia’s only planned port deep enough for them. For the Middle Corridor, that matters because Georgia is where cargo crossing the Caspian and the South Caucasus meets the sea route to Europe. A deep-water port lets larger ships carry corridor cargo onward to Romania, Bulgaria, the Mediterranean and beyond.

Kvrivishvili put the total cost of the project at about $1.1bn and said the first vessel is expected in 2029. She also pointed to the cargo case: transit cargo turnover in Georgia rose 21% year on year in January–April 2026, and 46% over four years.

Ten years of false starts

Anaklia has been Georgia’s most promised and most delayed infrastructure project.

  • 2016: the Anaklia Development Consortium, formed by Georgia’s TBC Holding and the US-based Conti Group, won the first contract to build and operate the port.
  • 2020: the government terminated the contract, saying the consortium had not secured financing.
  • 2024: a new tender selected a CCCC-led consortium for a 49% stake, with the state keeping 51%. The arrangement assumed about $600m of foreign direct investment.
  • April 2026: the port moved into active construction (see below).
  • July 2026: with the Chinese consortium gone, the government chose full state ownership.

Construction had already started

The change of model came three months after works began in earnest. On 24 April Deputy Economy Minister Tamar Ioseliani said that preparatory works were complete and the project had entered active construction. Belgium’s Jan De Nul, one of the world’s largest dredging and maritime construction companies, is carrying out the first stage: a breakwater of about 1.38 km to protect the harbour, and dredging of the access channel to roughly 18 metres. Ioseliani presented the port as part of a wider upgrade of Georgia’s railways, highways and air links, including a planned new international airport at Vaziani near Tbilisi.

Because the state was already paying for the marine works, the switch to a landlord model did not stop the site. It changes who pays for what comes next. SGBA described the start of works in April.

How a landlord port works

The landlord model is the most common way large ports are organised around the world, including Rotterdam and Antwerp. The port authority, usually public, owns the land, the breakwaters, the channels and often the quay walls. Private operators sign long-term leases or concessions for individual terminals and invest in cranes, yards and IT systems. They earn their money from handling fees, and the authority earns rent and port dues.

For Georgia, the model has three effects. It keeps ownership of a strategic asset in state hands, which the government sees as a guarantee against any single foreign partner gaining control. It turns one large, hard-to-finance concession into several smaller ones that different investors can bid for. And it shifts the first and riskiest spending, on marine works and core infrastructure, onto the state budget and its lenders.

The financing question

The 2024 arrangement assumed about $600m of foreign direct investment, which no longer exists. According to the Jamestown Foundation, the state now has to mobilise an additional $200m or so for berths and core infrastructure that the consortium was meant to fund.

Georgian experts are divided. Tinatin Khidasheli, head of the think tank Civic IDEA and a former defence minister, argued that Chinese banks remain the most likely source of capital. Paata Tsagareishvili of the Transport Corridor Research Center called the landlord model the only realistic alternative to the failed 2024 deal. Economists have also raised the question of how much more the state can borrow without pushing up public debt.

The port is one part of a larger programme. Georgia has said it plans about $7bn of investment in core transport and logistics infrastructure over the coming years, and a ten-year, $1.7bn modernisation of Georgian Railway announced in May. That railway plan includes an 18 km line to connect Anaklia to the national network. Georgian Railway’s director general, Lasha Abashidze, said the line is expected to take two to two and a half years to build. In October a World Bank-backed tender was published for consultants to supervise its design and construction, covered in a separate article.

Who is interested

Georgia has been courting Central Asian governments directly. In June Kvrivishvili met Kazakhstan’s Transport Minister, Nurlan Sauranbayev. On 4 July she toured the Anaklia site with two Uzbek ministers, Laziz Kudratov (Investment, Industry and Trade) and Ilhom Mahkamov (Transport). Uzbekistan expressed interest in having a presence in Georgia’s transport infrastructure, with an eye to cargo expected from the China–Kyrgyzstan–Uzbekistan railway now under construction.

What it means for business

  • Terminal operators and port investors: the landlord model creates several opportunities instead of one. Container, bulk, liquid and logistics terminals can be bid for separately, by different operators.
  • Contractors and engineers: marine works, berths, the rail link and supervision contracts will be tendered by the state and its lenders, often under international procurement rules.
  • Shippers: nothing changes before 2029. Until Anaklia opens, Black Sea cargo for the Middle Corridor goes through Poti, Batumi, Kulevi and Türkiye’s ports.
  • Central Asian governments and companies: a dedicated terminal on the Black Sea is on offer to partners willing to commit cargo and capital.

What to watch

  • Which international lenders finance the core works, and on what terms.
  • The first terminal tenders, their duration and who bids.
  • Progress on the 18 km rail link, which matters as much as the quay.
  • Whether Chinese companies return as terminal operators rather than as owners.

SGBA view

State ownership makes Anaklia slower to finance but harder to derail. After ten years of concessions that came and went, the state now controls the timetable, and the 2029 date depends less on politics than on Georgia’s ability to borrow. For investors, the opportunity has moved from the whole port to its terminals, which is a smaller ticket and an easier one to underwrite.

By SGBA. Figures as reported at the time of writing.

Sources

  1. Jamestown Foundation, Eurasia Daily Monitor, "Georgia's Anaklia pivots to state ownership", 16 July 2026
  2. Xinhua via The Star, "Georgia embarks on active construction of Anaklia port", 25 April 2026
  3. Imedi, "Georgia to invest $1.7 billion in railway overhaul over next decade, says Georgian PM", May 2026
  4. 1TV, "Georgian Railways announces start of railway infrastructure construction in Anaklia", 2026
  5. DevelopmentAid, World Bank TC-GATE supervision tender for the Anaklia railway link, 19 October 2026

SGBA checks every figure against the original source. How we work

Share LinkedIn X WhatsApp Email
Flagship report · Out 15 January 2027

Middle Corridor 2026: the Year in Review

The 10 events that defined the year, the corridor in numbers, a chapter for each country and industry, and the dates to watch in 2027. Free to download.